A petition
is required to establish a new drain or make improvements beyond
typical maintenance activities such as repairs to tile, removal
of accumulated sediment and debris, and repairs to eroded banks,
etc. The petitioning requirements vary for new, existing, or intercounty
drains. The Drain Commissioner or Drainage Board will select a qualified
engineer to design the drain construction or improvement project
including publishing, bidding, review of apportionments, etc.
After
receiving a petition the Drain Commissioner appoints three people
from outside the drainage district to serve as a Board of Determination.
Notices are mailed to the entire drainage district that a meeting
will be held to discuss the necessity of undertaking improvements
to the drain. If the Board of Determination believes that it is
necessary to improve the drain, they sign an Order of Determination
instructing the Drain Commissioner to construct a project to improve
the drain.
|